[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1277214,867,1,"单选题","( )是施工阶段质量控制的重点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工序的质量控制",true,{"key":16,"text":17,"correct":18},"B","材料的质量控制",false,{"key":20,"text":21,"correct":18},"C","人员的调度",{"key":23,"text":24,"correct":18},"D","设备仪器的使用","【知识点】 施工阶段质量控制的核心环节 【答案解析】 正确答案是A，工序的质量控制是施工阶段质量控制的重点，因为工程质量是通过一道道工序逐步形成的，控制工序质量是确保最终质量的关键。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]