[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277200":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1277200,867,1,"单选题","已完施工的成品保护问题和相应措施,在工程施工组织设计与计划阶段就应该在( )上进行考虑,防止( )不当或交叉作业造成相互干扰、污染和损坏。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工顺序施工顺序",true,{"key":16,"text":17,"correct":18},"B","施工质量施工质量",false,{"key":20,"text":21,"correct":18},"C","施工顺序施工质量",{"key":23,"text":24,"correct":18},"D","施工质量施工顺序","【知识点】 考察施工组织设计中成品保护与施工顺序的统筹安排。 【答案解析】 正确答案为A，因为成品保护需在施工顺序上提前规划，以防止施工顺序不当或交叉作业导致损坏，而非施工质量问题。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]