[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1277197,867,1,"单选题","建筑工程质量控制点中,不属于模板的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","位置、标高、尺寸",false,{"key":16,"text":17,"correct":14},"B","预埋件的位置",{"key":19,"text":20,"correct":14},"C","预留洞孔的位置",{"key":22,"text":23,"correct":24},"D","基础垫层标高",true,"【知识点】 考察模板工程质量控制点的内容。 【答案解析】 正确答案为D，基础垫层标高属于基础工程的控制点，而非模板工程的控制点；模板控制点包括位置、标高、尺寸、预埋件及预留洞孔位置等。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]