[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1276889":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1276889,866,2,"多选题","下列关于涂饰工程施工工艺的说法中,错误的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工工艺流程为:基层处理一打底、批刮腻子一面层施涂一修理",false,{"key":16,"text":17,"correct":18},"B","混凝土与抹灰表面在施涂前应将基体或基层的缺棱掉角处孔洞用1:2的水泥砂浆修补",true,{"key":20,"text":21,"correct":18},"C","外墙抗裂弹性腻子修补、填平时,待修补完成后,将抹灰面满刮外墙抗裂弹性腻子一遍,腻子批刮厚度为0.3～0.8mm",{"key":23,"text":24,"correct":18},"D","面层施涂滚涂大面时,用长度为15～20Cm的长辊,以利于提高功效",{"key":26,"text":27,"correct":14},"E","底漆和乳胶漆施工适宜温度为0℃以上,未用完的底乳胶漆应加盖密封,并存放在阴凉通风处","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"土建方向-通用基础","建筑工程",0]