[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1276579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1276579,866,1,"单选题","施工项目的劳动组织不包括下列的( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","劳务输入",false,{"key":16,"text":17,"correct":14},"B","劳动力组织",{"key":19,"text":20,"correct":14},"C","项目经理部对劳务队伍的管理",{"key":22,"text":23,"correct":24},"D","劳务输出",true,"",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-通用基础","建筑工程",0]