[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1276360":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1276360,865,2,"多选题","质量控制点选择的一般原则( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","施工中的薄弱环节,或质量不稳定的工序、部位或对象",true,{"key":16,"text":17,"correct":14},"B","施工过程中的关键工序或环节以及隐蔽工程",{"key":19,"text":20,"correct":14},"C","采用新技术、新工艺、新材料的部位或环节",{"key":22,"text":23,"correct":14},"D","施工上无足够把握的、施工条件困难的或技术难度大的工序或环节",{"key":25,"text":26,"correct":27},"E","工程量大的分项工程",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"土建方向-岗位技能","建筑工程",0]