[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1276240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1276240,865,1,"单选题","在( )阶段的质量控制,施工单位要严格按照审批的施工组织设计进行施工;对技术要求高,施工难度大的,或采用新工艺、新材料、新技术的工序和部位,须设置质量控制点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工准备",false,{"key":16,"text":17,"correct":18},"B","施工",true,{"key":20,"text":21,"correct":14},"C","竣工验收",{"key":23,"text":24,"correct":14},"D","使用","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]