[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1276239":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1276239,865,1,"单选题","以下哪项内容不是施工准备阶段质量控制的内容( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计交底和图纸会审",false,{"key":16,"text":17,"correct":14},"B","（质量计划）的审查",{"key":19,"text":20,"correct":14},"C","施工组织设计生产要素配置质量审查",{"key":22,"text":23,"correct":24},"D","隐蔽工程质量控制",true,"",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]