[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1276228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1276228,865,1,"单选题","为了保证工程能够顺利地施工,( )督促分包单位按照合同事先划定的范围,占有和使用现场有关部分。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术员",false,{"key":16,"text":17,"correct":18},"B","质量检查员",true,{"key":20,"text":21,"correct":14},"C","项目经理",{"key":23,"text":24,"correct":14},"D","监理","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]