[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1276129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1276129,865,1,"单选题","由于工程负责人片面追求施工进度,放松或不按质量标准进行控制和检验,人为降低施工质量标准。这个属于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","指导责任事故",true,{"key":16,"text":17,"correct":18},"B","操作责任事故",false,{"key":20,"text":21,"correct":18},"C","安全责任事故",{"key":23,"text":24,"correct":18},"D","设计责任事故","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]