[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275922":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275922,864,2,"多选题","下列关于土钉支护基坑施工的说法中,表述正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","一般采用施工机械,根据分层厚度和作业顺序开挖,一般每层开挖深度控制在100～150cm",true,{"key":16,"text":17,"correct":18},"B","土钉全长设施金属或塑料定位支架,间距5m,保证钢筋处于钻孔的中心部位",false,{"key":20,"text":21,"correct":14},"C","喷射混凝土粗骨料最大粒径不宜大于12mm,水胶比不宜大于0.45,并掺加速凝剂",{"key":23,"text":24,"correct":14},"D","喷射混凝土终凝后2h,应根据当地条件采取连续喷水养护5—7d或喷涂养护剂",{"key":26,"text":27,"correct":18},"E","冬期进行喷射混凝土,作业温度不得低于0℃,混合料进入喷射机的温度和水温不得低于0℃;在结冰的面层上不得喷射混凝土","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-通用基础","建筑工程",0]