[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275920":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275920,864,2,"多选题","下列关于砂石铺筑垫层施工说法错误的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","砂石铺筑分层、分段进行,每层厚度,一般为15—20cm,最大不超过50cm",true,{"key":16,"text":17,"correct":18},"B","分段施工时,接搓处应做成斜坡,每层接搓处的水平距离应错开0.5—1.0M,并应充分压（夯）实",false,{"key":20,"text":21,"correct":14},"C","采用压路机往复碾压,一般碾压不少于2遍,其轮距搭接不少于50cm",{"key":23,"text":24,"correct":18},"D","边缘和转角处应用人工或蛙式打夯机补夯密实",{"key":26,"text":27,"correct":18},"E","石灰稳定粒料类垫层与水泥稳定粒料类垫层都适用于城市道路温度和湿度状况不良的环境下","AC","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-通用基础","建筑工程",0]