[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275917":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275917,864,2,"多选题","下列关于沟槽开挖施工要点的说法中,错误的是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","当管径小、土方量少、施工现场狭窄、地下障碍物多或无法采用机械挖土时采用人工开挖",true,{"key":16,"text":17,"correct":14},"B","相邻沟槽开挖时,应遵循先深后浅的施工顺序",{"key":19,"text":20,"correct":21},"C","采用机械挖土时,应使槽底留50cm左右厚度土层,由人工清槽底",false,{"key":23,"text":24,"correct":21},"D","已有地下管线与沟槽交叉或邻近建筑物、电杆、测量标志时,应采取避开措施",{"key":26,"text":27,"correct":14},"E","穿越道路时,架设施工临时便桥,设置明显标志,做好交通导行措施","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-通用基础","建筑工程",0]