[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275916":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275916,864,2,"多选题","喷锚暗挖（矿山）法中沉降量大、工期长的开挖方式有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","双侧壁导坑法",true,{"key":16,"text":17,"correct":18},"B","交叉中隔壁法（CRD工法）",false,{"key":20,"text":21,"correct":18},"C","中洞法",{"key":23,"text":24,"correct":14},"D","侧洞法",{"key":26,"text":27,"correct":14},"E","柱洞法","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-通用基础","建筑工程",0]