[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275912":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275912,864,2,"多选题","下列关于GCL垫质量控制要点的说法中,表述正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","填埋区基底检验合格后方可进行GCL垫铺设作业,每一工作面施工前均要对基底进行修整和检验",true,{"key":16,"text":17,"correct":18},"B","对铺开的GCL垫进行调整,调整搭接宽度,控制在450mm±50mm范围内,拉平GCL垫,确保无褶皱、无悬空现象,与基础层贴实",false,{"key":20,"text":21,"correct":14},"C","掀开搭接处上层GCL垫,在搭接处均匀撒膨润土粉,将两层垫间密封,然后将掀开的GCL垫铺回",{"key":23,"text":24,"correct":14},"D","根据填埋区基底设计坡向,CCL垫的搭接,尽量采用顺坡搭接,即采用上压下的搭接方式;注意避免出现十字搭接,而尽量采用品形分布",{"key":26,"text":27,"correct":14},"E","GCL垫需当日铺设当日覆盖,遇有雨雪天气停止施工,并将已铺设的GCL垫覆盖好","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-通用基础","建筑工程",0]