[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275867":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275867,864,2,"多选题","下列关于高压喷射注浆法的各项中,正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工前进行试桩,确定施工工艺和技术参数,作为施工控制依据,试桩数量不应少于2根",true,{"key":16,"text":17,"correct":18},"B","水泥浆液的水胶比按要求确定,可取0.3~1.5,常用为1.0",false,{"key":20,"text":21,"correct":18},"C","注浆管分段提升的搭接长度一般大于50mm",{"key":23,"text":24,"correct":14},"D","钻机与高压泵的距离不宜大于50m",{"key":26,"text":27,"correct":14},"E","高压喷射注浆完毕,可在原孔位采用冒浆回灌或第二次注浆等措施","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-通用基础","建筑工程",0]