[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275864":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275864,864,2,"多选题","沉管工程施工方案主要内容包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工平面布置图及剖面图",true,{"key":16,"text":17,"correct":18},"B","施工总平面布置图",false,{"key":20,"text":21,"correct":14},"C","沉管施工方法的选择及相应的技术要求",{"key":23,"text":24,"correct":14},"D","沉管施工各阶段的管道浮力计算,并根据施工方法进行施工各阶段的管道强度、刚度、稳定性验算",{"key":26,"text":27,"correct":14},"E","水上运输航线的确定,通航管理措施","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-通用基础","建筑工程",0]