[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275862":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275862,864,2,"多选题","以下各项中属于施工现场管理的内容的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","落实资源进度计划",false,{"key":16,"text":17,"correct":18},"B","施工平面布置",true,{"key":20,"text":21,"correct":18},"C","施工现场封闭管理",{"key":23,"text":24,"correct":14},"D","施工资源进度计划的动态调整",{"key":26,"text":27,"correct":18},"E","警示标牌","BCE","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-通用基础","建筑工程",0]