[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275677":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1275677,863,3,"判断题","制定项目质量控制程序即根据项目部施工管理的基本程序,结合项目具体特点,在制定项目总体质量计划后,列出施工过程阶段、节点和总体质量水平有影响的项目,作为施工重点。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"",{"id":6,"name":21,"category":22,"favorite":23},"市政方向-岗位技能","建筑工程",0]