[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275605":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1275605,863,3,"判断题","施工阶段质量控制是整个工程质量控制的重点。根据工程项目质量目标要求,加强对施工现场及施工工艺的监督管理,重点控制工序质量,督促施工人员严格按设计施工图纸、施工工艺、国家有关质量标准和操作规程进行施工和管理。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"",{"id":6,"name":21,"category":22,"favorite":23},"市政方向-岗位技能","建筑工程",0]