[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275438":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275438,863,2,"多选题","分部（子分部）工程应由施工单位将自行检查评定合格的表格填好后,由项目负责人交( )验收。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","勘察单位",{"key":23,"text":24,"correct":14},"D","监理单位",{"key":26,"text":27,"correct":18},"E","总承包单位","AD","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-岗位技能","建筑工程",0]