[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275173":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1275173,862,2,"多选题","下列选项中属于项目资源管理计划编制依据的是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同文件",true,{"key":16,"text":17,"correct":14},"B","现场文件",{"key":19,"text":20,"correct":21},"C","投标文件",false,{"key":23,"text":24,"correct":14},"D","项目管理实施规划",{"key":26,"text":27,"correct":14},"E","项目进度计划","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"设备方向-通用基础","建筑工程",0]