[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275049":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1275049,862,1,"单选题","对隐蔽工程的验收,施工单位应进行自检,并在隐蔽或在中间验收前( )h以书面形式通知监理工程师验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","24",false,{"key":16,"text":17,"correct":18},"B","48",true,{"key":20,"text":21,"correct":14},"C","36",{"key":23,"text":24,"correct":14},"D","72","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-通用基础","建筑工程",0]