[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1275036,862,1,"单选题","项目经理部应依据施工条件,按照( )、施工方案和施工进度计划要求,认真进行所负责区域的施工平面图的规划、设计等内容。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","初步设计图",false,{"key":16,"text":17,"correct":14},"B","施工合同",{"key":19,"text":20,"correct":14},"C","扩大初步设计图",{"key":22,"text":23,"correct":24},"D","施工总平面图",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-通用基础","建筑工程",0]