[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275015":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1275015,862,1,"单选题","卫生器具安装正确的工艺流程是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装准备→卫生器具及配件检验→卫生器具安装→卫生器具配件预装→卫生器具稳装→卫生器具与墙、地缝隙处理→卫生器具外观检查→通水试验",true,{"key":16,"text":17,"correct":18},"B","安装准备→卫生器具及配件检验→卫生器具安装→卫生器具配件稳装→卫生器具预装→卫生器具与墙、地缝隙处理→卫生器具外观检查→通水试验",false,{"key":20,"text":21,"correct":18},"C","安装准备→卫生器具及配件检验→卫生器具稳装→卫生器具配件预装→卫生器具安装→卫生器具与墙、地缝隙处理→卫生器具外观检查→通水试验",{"key":23,"text":24,"correct":18},"D","安装准备→卫生器具及配件检验→卫生器具稳装→卫生器具配件安装→卫生器具预装→卫生器具与墙、地缝隙处理→卫生器具外观检查→通水试验","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-通用基础","建筑工程",0]