[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275013":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1275013,862,1,"单选题","室外铸铁给水管安装的工艺流程是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管道预制→布管、下管→管道对口、调直稳固→管道连接→试压、冲洗、消毒→土方回填",true,{"key":16,"text":17,"correct":18},"B","管道预制→管道对口、调直稳固→布管、下管→管道连接→试压、冲洗、消毒→土方回填",false,{"key":20,"text":21,"correct":18},"C","管道预制→布管、下管→试压、冲洗、消毒→管道连接→管道对口、调直稳固→土方回填",{"key":23,"text":24,"correct":18},"D","管道预制→试压、冲洗、消毒→管道对口、调直稳固→管道连接→布管、下管→土方回填","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-通用基础","建筑工程",0]