[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1275000":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1275000,862,1,"单选题","送电验收工作中,需送电空载运行( )h,无异常现象,办理验收手续,交建设单位使用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":21},"C","24",true,{"key":23,"text":24,"correct":14},"D","48","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-通用基础","建筑工程",0]