[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274698":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1274698,861,2,"多选题","项目的质量体系应从( )几个方面建立质量体系,实现对影响质量的施工全过程的有效控制。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","组织结构",true,{"key":16,"text":17,"correct":14},"B","责任与权限",{"key":19,"text":20,"correct":14},"C","运作程序",{"key":22,"text":23,"correct":14},"D","路径工程",{"key":25,"text":26,"correct":14},"E","资源","ABCDE","",{"id":6,"name":30,"category":31,"favorite":32},"设备方向-岗位技能","建筑工程",0]