[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274695":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274695,861,2,"多选题","质量计划编制依据是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程施工合同及相关的协议",true,{"key":16,"text":17,"correct":18},"B","施工方案",false,{"key":20,"text":21,"correct":14},"C","已批准的初步设计及有关的图纸资料",{"key":23,"text":24,"correct":14},"D","工程概算和主要工程量",{"key":26,"text":27,"correct":14},"E","现场情况调查资料","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"设备方向-岗位技能","建筑工程",0]