[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274678":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274678,861,2,"多选题","从试验状态划分,设备安装工程试验划分为静态试验和动态考核两类,动态考核又分为( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","单机试运转",true,{"key":16,"text":17,"correct":14},"B","无负荷试运转",{"key":19,"text":20,"correct":14},"C","负荷试运转",{"key":22,"text":23,"correct":14},"D","系统联合试运转",{"key":25,"text":26,"correct":27},"E","动力设备受电力驱使而运转",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备方向-岗位技能","建筑工程",0]