[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274674":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1274674,861,2,"多选题","设备安装工程试运行的条件( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","试运行的方案已批准",true,{"key":16,"text":17,"correct":14},"B","试运行范围内的工程已按合同约定全部完工,并经自检静态查质量合格",{"key":19,"text":20,"correct":14},"C","试运行所需的电力、供水、供气均接人到位",{"key":22,"text":23,"correct":14},"D","试运行涉及的环境、场地已清理",{"key":25,"text":26,"correct":14},"E","对试运行准备工作进行查检,确认符合方案要求","ABCDE","",{"id":6,"name":30,"category":31,"favorite":32},"设备方向-岗位技能","建筑工程",0]