[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274673":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1274673,861,2,"多选题","管道试压的步骤( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","接好试压泵",true,{"key":16,"text":17,"correct":14},"B","关闭人口总阀和所有泄水阀门和低处泄水阀门",{"key":19,"text":20,"correct":14},"C","打开系统内的各支路及主干管的阀门",{"key":22,"text":23,"correct":14},"D","打开系统内最高处的排气阀门",{"key":25,"text":26,"correct":14},"E","打开试压用水源阀门,系统充水","ABCDE","",{"id":6,"name":30,"category":31,"favorite":32},"设备方向-岗位技能","建筑工程",0]