[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274655":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274655,861,2,"多选题","施工过程发生设计变更信息传递中断而造成质量问题的事件应怎样整改( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对资料员进行培训,以提高其业务能力和责任心",true,{"key":16,"text":17,"correct":14},"B","对项目部质量管理体系文件做评估,补充、修改和完善其不足的部分",{"key":19,"text":20,"correct":21},"C","调换技术人员",false,{"key":23,"text":24,"correct":21},"D","更换应用设备",{"key":26,"text":27,"correct":21},"E","对施工员进行培训,以提高其业务能力和责任心","AB","",{"id":6,"name":31,"category":32,"favorite":33},"设备方向-岗位技能","建筑工程",0]