[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274651":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274651,861,2,"多选题","PP-R热熔管路试压要注意的问题( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","系统试压应在最后一个管口连接后降至常温才能试压",true,{"key":16,"text":17,"correct":14},"B","实验压力值为告知压力的1.5倍,但不小于0.6MPa",{"key":19,"text":20,"correct":14},"C","试压时应在实验压力下稳压th,压力降不得超过0.05MPa",{"key":22,"text":23,"correct":24},"D","在工作压力的1.5倍状态下稳压2h,压力降不得超过0.03MPa",false,{"key":26,"text":27,"correct":14},"E","在工作压力的1.15倍状态下稳压2h,压力降不得超过0.03MPa","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"设备方向-岗位技能","建筑工程",0]