[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274650":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1274650,861,2,"多选题","施工员与质量员会同编制的质量交底文件有哪些方面( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设备的外观检查和施工专业的环境条件",true,{"key":16,"text":17,"correct":14},"B","盘柜基础型钢制作安装、盘柜的搬运和盘柜的就位",{"key":19,"text":20,"correct":14},"C","盘柜内二次回电路接线及检查",{"key":22,"text":23,"correct":14},"D","电气调试和整定",{"key":25,"text":26,"correct":14},"E","盘柜的受电和送电","ABCDE","",{"id":6,"name":30,"category":31,"favorite":32},"设备方向-岗位技能","建筑工程",0]