[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1274612,861,1,"单选题","现行的《建筑给水排水及采暖工程施工质量验收规范》GB50242-2002中要求盘管隐蔽前必须进行( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","满水实验",false,{"key":16,"text":17,"correct":14},"B","灌水实验",{"key":19,"text":20,"correct":21},"C","水压实验",true,{"key":23,"text":24,"correct":14},"D","注水实验","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]