[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1274571,861,1,"单选题","项目质量体系文件不包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管理性文件",false,{"key":16,"text":17,"correct":14},"B","纲领性文件",{"key":19,"text":20,"correct":21},"C","施工性文件",true,{"key":23,"text":24,"correct":14},"D","执行性文件","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]