[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1274564,861,1,"单选题","不属于质量计划编制依据( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设备清单及主要材料或大宗材料清单",false,{"key":16,"text":17,"correct":14},"B","现场情况调查资料",{"key":19,"text":20,"correct":14},"C","新材料、新工艺的使用说明或试验资料",{"key":22,"text":23,"correct":24},"D","施工方案",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]