[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274562":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1274562,861,1,"单选题","质量计划编制的主要内容,施工部署不包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定施工进度计划、质量和安全目标",false,{"key":16,"text":17,"correct":14},"B","确定环境保护和降低施工成本措施",{"key":19,"text":20,"correct":21},"C","加快事故进度",true,{"key":23,"text":24,"correct":14},"D","确定施工顺序和施工组织管理体系","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]