[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274560":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1274560,861,1,"单选题","质量计划编制的主要内容,主要的施工方案不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主要主项工程施工工艺及工序的确定,样板区的选定",true,{"key":16,"text":17,"correct":18},"B","主要的施工机械的选配",false,{"key":20,"text":21,"correct":18},"C","季节性施工的步骤和防台防雨措施",{"key":23,"text":24,"correct":18},"D","构件配件的加工订货或自行制作的选定","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]