[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274241":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1274241,860,3,"判断题","建设工程项目质量控制体系，一般形成全方位、立体化的结构形态，这是由其实施任务的委托方式和合同结构所决定的。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"建设工程项目质量控制体系，一般形成多层次、多单元的结构形态，这是由其实施任务的委托方式和合同结构所决定的。",{"id":6,"name":21,"category":22,"favorite":23},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]