[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274214":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274214,860,2,"多选题","单位（子单位）工程质量验收合格应符合下列规定（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","单位（子单位）工程所含部分（子分部）工程的质量均应验收合格",true,{"key":16,"text":17,"correct":14},"B","质量控制资料应完整",{"key":19,"text":20,"correct":14},"C","单位（子单位）工程所含分部工程有关安全和功能的检测资料应完整",{"key":22,"text":23,"correct":24},"D","主要功能项目的调查结果部分符合相关专业质量验收规范的规定",false,{"key":26,"text":27,"correct":14},"E","观感质量验收应符合要求","ABCE","建筑工程施工质量要求：单位（子单位）工程质量验收合格应符合下列规定1）单位（子单位）工程所含部分（子分部）工程的质量均应验收合格；2）质量控制资料应完整；3）单位（子单位）工程所含分部工程有关安全和功能的检测资料应完整；4）主要功能项目的抽查结果应符合相关专业质量验收规范的规定；5）观感质量验收应符合要求。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]