[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274196":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274196,860,2,"多选题","《建筑节能工程施工质量验收规范》GB50411—2007，强制性条文中：墙体节能工程的施工应符合下列那些规定（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","保温浆料待结构成型后统一施工",false,{"key":16,"text":17,"correct":18},"B","保温隔热材料的厚度必须符合设计要求",true,{"key":20,"text":21,"correct":18},"C","保温板与基层及各构层之间的粘结或连接必须牢固",{"key":23,"text":24,"correct":18},"D","当墙体节能工程的保温层采取预埋或后置锚固件固定时，锚固件数量、位置、锚固深度和拉拔力应符合设计要求",{"key":26,"text":27,"correct":14},"E","各种设备、总控阀门与仪表应按设计要求安装齐全，不得随意增减和更换","BCD","建筑节能工程施工质量验收规范》GB50411—2007，强制性条文中：墙体节能工程的施工应符合下列规定：1、保温隔热材料的厚度必须符合设计要求；2、保温板与基层及各构层之间的粘结或连接必须牢固；3、保温浆料应分层施工；4、当墙体节能工程的保温层采取预埋或后置锚固件固定时，锚固件数量、位置、锚固深度和拉拔力应符合设计要求。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]