[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274069":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274069,860,2,"多选题","抹灰工程的施工质量控制点的预防措施（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","基层应清理干净，抹灰前要浇水湿润，注意砂浆配合比，使底层砂浆与楼板粘结牢固；抹灰时应分层分遍压实，施工完后及时浇水养护",true,{"key":16,"text":17,"correct":14},"B","抹灰前要认真用托线板、靠尺对抹灰墙面尺寸预测摸底，安排好阴阳角不同两个面的灰层厚度和方正，认真做好灰饼、冲筋",{"key":19,"text":20,"correct":14},"C","踢脚板、墙裙施工操作要仔细，认真吊垂直、拉通线找直找方，抹完灰后用板尺将上口刮平、压实、赶光",{"key":22,"text":23,"correct":24},"D","在墙面和地面相交的阴角处，出地面管道根部和地漏周围，应先做防水附加层",false,{"key":26,"text":27,"correct":14},"E","要采用同品种、同强度等级的水泥，严禁混用，防止颜色不均；接槎应避免在块中，应甩在分格条外","ABCE","抹灰工程的施工质量控制点的预防措施：①基层应清理干净，抹灰前要浇水湿润，注意砂浆配合比，使底层砂浆与楼板粘结牢固；抹灰时应分层分遍压实，施工完后及时浇水养护。②抹灰前要认真用托线板、靠尺对抹灰墙面尺寸预测摸底，安排好阴阳角不同两个面的灰层厚度和方正，认真做好灰饼、冲筋；阴阳角处用方尺套方，做到墙面垂直、平顺、阴阳角方正。③踢脚板、墙裙施工操作要仔细，认真吊垂直、拉通线找直找方，抹完灰后用板尺将上口刮平、压实、赶光。④要采用同品种、同强度等级的水泥，严禁混用，防止颜色不均；接槎应避免在块中，应甩在分格条外。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]