[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274068":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274068,860,2,"多选题","地面面砖工程的施工质量控制点的预防措施（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","地面砖釉面色差及棱边缺损，面砖规格偏差翘曲",false,{"key":16,"text":17,"correct":18},"B","施工前地面砖需要挑选，将颜色、花纹、规格尺寸相同的砖挑选出来备用",true,{"key":20,"text":21,"correct":18},"C","地面基层一定要清理干净，地砖在施工前必须提前浇水湿润，保证含水率",{"key":23,"text":24,"correct":18},"D","地面铺装时一定要做出灰饼标高，拉线找直，水平尺随时检查平整度",{"key":26,"text":27,"correct":18},"E","有防水要求的房间，按照设计要求找出房间的流水方向找坡","BCDE","地面面砖工程的施工质量控制点的预防措施：①施工前地面砖需要挑选，将颜色、花纹、规格尺寸相同的砖挑选出来备用。②地面基层一定要清理干净，地砖在施工前必须提前浇水湿润，保证含水率，地面铺装砂浆时应先将板块试铺后，检查干硬性砂浆的密实度，安装时用橡皮锤敲实，保证不出现空鼓、断裂。③地面铺装时一定要做出灰饼标高，拉线找直，水平尺随时检查平整度；擦缝要仔细。④有防水要求的房间，按照设计要求找出房间的流水方向找坡；套割仔细。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]