[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274063":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274063,860,2,"多选题","门窗工程的施工控制点的预防措施包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","基层应清理干净.抹灰前要浇水湿润.注意砂浆配合比.使底层砂浆与楼板粘结牢固；抹灰时应分层分遍压实.施工完后及时浇水养护",false,{"key":16,"text":17,"correct":14},"B","抹灰前要认真用托线板、靠尺对抹灰墙面尺寸预测摸底.安排好阴阳角不同两个面的灰层厚度和方正.认真做好灰饼、冲筋",{"key":19,"text":20,"correct":21},"C","砌筑时上下左右拉线找规矩.一般门窗框上皮应低于门窗过梁10～15mm.窗框下比窗台上皮高5mm。",true,{"key":23,"text":24,"correct":21},"D","铰链位置距门窗上下端宜取立梃高度的1\u002F10",{"key":26,"text":27,"correct":21},"E","安装人员必须按照工艺要点施工.安装前先弹线找规矩.做好准备工作后.先安样板.合格后再全面安装","CDE","门窗工程的施工控制点的预防措施：1）砌筑时上下左右拉线找规矩，一般门窗框上皮应低于门窗过梁10～15mm，窗框下皮应比窗台上皮高5mm。2）铰链位置距门窗上下端宜取立梃高度的1\u002F10；安装铰链时，必须按画好的铰链位置线开凿铰链槽，槽深砬比铰链厚度大1-2mm；根据铰链规格选用合适的木螺钉，木螺钉可用锤打入1\u002F3深后，再行拧入。3）安装人员必须按照工艺要点施1，安装前先弹线找规矩，做好准备工作后，先安样板，合格后再全面安装。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]