[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274062":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274062,860,2,"多选题","现场施工准备工作的质量控制包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","计量控制",true,{"key":16,"text":17,"correct":14},"B","测量控制",{"key":19,"text":20,"correct":21},"C","工程质量控制",false,{"key":23,"text":24,"correct":14},"D","施工平面图控制",{"key":26,"text":27,"correct":14},"E","工程质量检查验收的划分项目","ABDE","现场施工准备工作的质量控制：1、计量控制；2、测量控制；3、施工平面图控制；4、工程质量检查验收的划分项目。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]