[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274045":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274045,860,2,"多选题","饰面板（砖）工程的施工质量控制点的预防措施：（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","石材挑选，色差，返碱，水渍",false,{"key":16,"text":17,"correct":18},"B","石材选样后进行封样，按照选样石材，对进场的石材检验挑选，对于色差较大的应进行更换",true,{"key":20,"text":21,"correct":18},"C","严格按照设计要求的骨架固定方式，固定牢固，后置埋件应做现场拉拔试验，必须按要求刷防锈漆处理",{"key":23,"text":24,"correct":18},"D","安装石材应吊垂直线和拉水平线控制，避免出现高低差",{"key":26,"text":27,"correct":18},"E","石材在运输、二次加工、安装过程中注意不要磕碰","BCDE","饰面板（砖）工程的施工质量控制点的预防措施：①石材选样后进行封样，按照选样石材，对进场的石材检验挑选，对于色差较大的应进行更换。湿作业施工前应对石材侧面和背面进行返碱背涂处理。②严格按照设计要求的骨架固定方式，固定牢固，后置埋件应做现场拉拔试验，必须按要求刷防锈漆处理。③安装石材应吊垂直线和拉水平线控制，避免出现高低差。④石材在运输、二次加工、安装过程中注意不要磕碰。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]