[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274041":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274041,860,2,"多选题","根据《建筑工程施工质量验收统一标准》GB50300--2001的规定，建筑工程质量验收应逐级划分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","配置必要的计量人员",false,{"key":16,"text":17,"correct":18},"B","单位（子单位）工程",true,{"key":20,"text":21,"correct":18},"C","分部（子分部）工程",{"key":23,"text":24,"correct":18},"D","分项工程和检验批",{"key":26,"text":27,"correct":14},"E","审核相关质量文件","BCD","根据《建筑工程施工质量验收统一标准》GB50300--2001的规定，建筑工程质量验收应逐级划分为单位（子单位）工程、分部（子分部）工程、分项工程和检验批。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]