[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274040":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274040,860,2,"多选题","事后控制包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","明示或者暗示施工单位使用不合格的建筑材料、建筑构配件和设备的",false,{"key":16,"text":17,"correct":18},"B","对质量活动结果的评价、认定",true,{"key":20,"text":21,"correct":18},"C","对工序质量偏差的纠正",{"key":23,"text":24,"correct":14},"D","对施工现场存在的重大安全隐患未向建设主管部门报告",{"key":26,"text":27,"correct":18},"E","对不合格产品进行整改和处理。","BCE","事后控制包括对质量活动结果的评价、认定；对工序质量偏差的纠正；对不合格产品进行整改和处理。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]